- Star Road is closed for the duration of the project.
- Intermountain Gas company welding pipe for boring.
- Lumen relocating their utility.
- Dewatering starting December 18th.
Share December 1, 2023 on Facebook
Share December 1, 2023 on X (formerly Twitter)
Share December 1, 2023 on Linkedin
Email December 1, 2023 link
This project is substantially complete.