December 15, 2023

  • Star Road is closed for the duration of the project.
  • Intermountain Gas company welding pipe for boring - Boring Ongoing.
  • Lumen complete relocating lines.
  • Dewatering starting December 18th.
Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link

This project is substantially complete. 