August 2, 2024

02 Aug 2024
  • Removing concrete and placing pole foundations.
  • Storm drain work is complete.
  • Sidewalk being formed south side of University Drive - Ongoing.
Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link

This project is substantially complete. 