  • Removing concrete and placing pole foundations.
  • Placing curb and sidewalk on north side of University Drive.
  • Storm drain complete.
  • Sidewalk being formed south side of University.
  • Standing poles July 25th.
Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete. 