  • Started on Juanita Street.
  • Removing concrete and placing pole foundations.
  • Placing curb and sidewalk on north side of University Drive.
  • Paving at Brady anticipated June 21st.
  • Starting south side of University on June 17th.
Share June 21, 2024 on Facebook Share June 21, 2024 on X (formerly Twitter) Share June 21, 2024 on Linkedin Email June 21, 2024 link

This project is substantially complete. 