July 19, 2024
- Preconstruction meeting was held May 30th.
- Apple/Victory - All sidewalk placed.
- Sawcutting for paving on July 18th.
- Paving anticipated the week of July 22nd.
- RRFB ongoing.
- 42nd/43rd - Curb and Sidewalk complete.
- RRFB ongoing.
- Waiting for concrete to cure.
- Paving anticipated starting June 26th.
Share July 19, 2024 on Facebook
Share July 19, 2024 on Twitter
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.