July 19, 2024
- Preconstruction meeting was held May 30th.
- Apple/Victory - All sidewalk placed.
- Sawcutting for paving on July 18th.
- Paving anticipated the week of July 22nd.
- RRFB ongoing.
- 42nd/43rd - Curb and Sidewalk complete.
- RRFB ongoing.
- Waiting for concrete to cure.
- Paving anticipated starting June 26th.
Share July 19, 2024 on Facebook
Share July 19, 2024 on X (formerly Twitter)
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.