July 19, 2024

  • Preconstruction meeting was held May 30th.
  • Apple/Victory - All sidewalk placed.
    • Sawcutting for paving on July 18th.
    • Paving anticipated the week of July 22nd.
    • RRFB ongoing.
  • 42nd/43rd - Curb and Sidewalk complete.
    • RRFB ongoing.
    • Waiting for concrete to cure.
    • Paving anticipated starting June 26th.
Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete. 