July 26, 2024

  • Preconstruction meeting was held May 30th.
  • Apple/Victory - All sidewalk placed. Asphalt paving was done July 23rd. RRFB ongoing.
  • Adams and 42nd/43rd - Curb and sidewalk complete. RRFB ongoing. Waiting for concrete to cure. Paving anticipated starting July 26th.
Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link

This project is substantially complete. 