July 26, 2024
- Preconstruction meeting was held May 30th.
- Apple/Victory - All sidewalk placed. Asphalt paving was done July 23rd. RRFB ongoing.
- Adams and 42nd/43rd - Curb and sidewalk complete. RRFB ongoing. Waiting for concrete to cure. Paving anticipated starting July 26th.