July 26, 2024

  • Preconstruction meeting was held May 30th.
  • Apple/Victory - All sidewalk placed. Asphalt paving was done July 23rd. RRFB ongoing.
  • Adams and 42nd/43rd - Curb and sidewalk complete. RRFB ongoing. Waiting for concrete to cure. Paving anticipated starting July 26th.
Share July 26, 2024 on Facebook Share July 26, 2024 on X (formerly Twitter) Share July 26, 2024 on Linkedin Email July 26, 2024 link

This project is substantially complete. 