Warm Springs Pedestrian Crossings: Sky Bar & Maynard

Share on Facebook Share on Twitter Share on Linkedin Email this link

Project is substantially complete. 

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Warm Springs Avenue Pedestrian Crossings at Sky Bar Street and Maynard Avenue. Construction is expected to be complete early fall of 2023.

The purpose of the project is to provide additional enhanced crosswalks on Warm Springs Avenue and increase safety for those crossing the road.

About RRFBs

When activated by pedestrians pushing the button, RRFBs flash in a distinct pattern, alerting drivers that pedestrians are actively in the crosswalk.

RRFBs have several distinct advantages in enhancing existing marked crosswalks:

  • Increased pedestrian/bicyclist visibility.
  • Reduction in pedestrian crashes.
  • Increased safety with drivers more likely to stop for pedestrians/bicyclists using the crosswalk.

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Warm Springs Avenue Pedestrian Crossings at Sky Bar Street and Maynard Avenue. Construction is expected to be complete early fall of 2023.

The purpose of the project is to provide additional enhanced crosswalks on Warm Springs Avenue and increase safety for those crossing the road.

About RRFBs

When activated by pedestrians pushing the button, RRFBs flash in a distinct pattern, alerting drivers that pedestrians are actively in the crosswalk.

RRFBs have several distinct advantages in enhancing existing marked crosswalks:

  • Increased pedestrian/bicyclist visibility.
  • Reduction in pedestrian crashes.
  • Increased safety with drivers more likely to stop for pedestrians/bicyclists using the crosswalk.

Project is substantially complete. 

  • September 15, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Work nearly complete.
    • Waiting on pavement markings.
  • August 31, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Signs and striping remain.
  • August 25, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Warm Springs & Maynard - Sidewalks and signs placed. Paving anticipated for August 25th.
    • Warm Springs & Skybar - Sidewalk and curb placed. Paving anticipated August 25th. Pavement markings scheduled for the week of August 28th.
  • August 18, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Warm Springs and Maynard - placing sidewalk
    • Warm Springs and Skybar - sidewalk and curb remaining.
  • August 11, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Maynard prepped and ready for sidewalk.
    • Skybar - RRFB poles set.
    • Removing asphalt.
  • August 9, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Poles are placed.
    • Paving greenbelt path
    • Sidewalk anticipated being placed August 4th to connect to greenbelt.
  • July 28, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Contractor started July 10th at Maynard
    • Temp paving to widen Warm Springs
    • Installed ped detour on greenbelt
    • Forming and placing signal poles