13th Street and Washington Street Pedestrian Crossing Project

Share 13th Street and Washington Street Pedestrian Crossing Project on Facebook Share 13th Street and Washington Street Pedestrian Crossing Project on X (formerly Twitter) Share 13th Street and Washington Street Pedestrian Crossing Project on Linkedin Email 13th Street and Washington Street Pedestrian Crossing Project link

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the 13th Street and Washington Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete by late summer 2026.*

Project Description

  • Install an enhanced pedestrian crossing at 13th Street and Washington Street
  • Improve pavement markings
  • Install a bulb-out on the northwest corner and reconstruct adjacent pedestrian ramps to meet current standards
  • Install updated storm drainage infrastructure to help manage rainwater

*Construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the 13th Street and Washington Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete by late summer 2026.*

Project Description

  • Install an enhanced pedestrian crossing at 13th Street and Washington Street
  • Improve pavement markings
  • Install a bulb-out on the northwest corner and reconstruct adjacent pedestrian ramps to meet current standards
  • Install updated storm drainage infrastructure to help manage rainwater

*Construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link
    • 13th Street is closed.
    • Paving July 9th.
    • Minor work remains, including landscaping, manhole adjustments, & permanent pavement markings.
    • 13th Street is closed.
    • Paving July 9th.
    • Minor work remains, including landscaping, manhole adjustments, & permanent pavement markings.
  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link
    • 13th Street is closed.
    • Pole bases set.
    • Concrete being prepped.
    • Paving anticipated for the week of June 29th.
    • 13th Street is closed.
    • Pole bases set.
    • Concrete being prepped.
    • Paving anticipated for the week of June 29th.
  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Pole bases set.
    • Concrete being prepped.
    • Paving anticipated for the week of June 29th.
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Pole bases set.
    • Concrete being prepped.
    • Paving anticipated for the week of June 29th.
  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Pole bases being set.
    • Concrete being prepped.
    • Paving anticipated week of June 29th.
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Pole bases being set.
    • Concrete being prepped.
    • Paving anticipated week of June 29th.
  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 link
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Started pipe work June 8th - Ongoing.
    • Pole bases being set.
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Started pipe work June 8th - Ongoing.
    • Pole bases being set.
  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Starting pipe work June 8th.
    • Pole bases are being set.
    • 13th Street is closed.
    • Removing sidewalk panels.
    • Asphalt removed.
    • Starting pipe work June 8th.
    • Pole bases are being set.
Page last updated: 09 Jul 2026, 03:08 PM