July 26, 2024

  • 15th & Front is substantially complete. RRFB has been activated.
  • At 16th & Front, concrete work and asphalt paving is complete.
  • Remaining work includes permanent striping and RRFB activation.
  • Front Street will be closed between 16th & 17th through the end of July.
Share July 26, 2024 on Facebook Share July 26, 2024 on X (formerly Twitter) Share July 26, 2024 on Linkedin Email July 26, 2024 link

This project is substantially complete. 