June 28, 2024

  • 15th & Front is substantially complete.
  • RRFB has been activated.
  • Work on the east side of 16th & Front started May 29th.
  • Front Street will be closed between 15th & 16th through early July.
  • Work on the west side of 16th & Front is scheduled for July.
Share June 28, 2024 on Facebook Share June 28, 2024 on X (formerly Twitter) Share June 28, 2024 on Linkedin Email June 28, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>