June 7, 2024

  • 15th & Front is substantially complete. RRFB has been activated.
  • Work on the east side of 16th & Front started May 29th. Front Street will be closed between 15th & 16th through the end of June.
  • Work on the west side of 16th & Front is scheduled for July.
Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link

This project is substantially complete. 