-
Share June 20, 2025 on Facebook
Share June 20, 2025 on X (formerly Twitter)
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
Work on the west side of the intersection began May 12th
o Electrical work ongoing
o Pavement markings and signs remaining
Work on the west side of the intersection began May 12th
o Electrical work ongoing
o Pavement markings and signs remaining
This project is substantially complete.
-
Share June 13, 2025 on Facebook
Share June 13, 2025 on X (formerly Twitter)
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
- Concrete intersection complete.
- Landscaping ongoing.
- Asphalt paving anticipated the week of June 16th.
- Concrete intersection complete.
- Landscaping ongoing.
- Asphalt paving anticipated the week of June 16th.
This project is substantially complete.
-
Share June 6, 2025 on Facebook
Share June 6, 2025 on X (formerly Twitter)
Share June 6, 2025 on Linkedin
Email June 6, 2025 link
- Placed pole bases.
- Ped ramps placed.
- Valley gutter and sidewalk anticipate being completed by June 5th.
- Concrete intersection ongoing.
- Placed pole bases.
- Ped ramps placed.
- Valley gutter and sidewalk anticipate being completed by June 5th.
- Concrete intersection ongoing.
This project is substantially complete.
-
Share May 30, 2025 on Facebook
Share May 30, 2025 on X (formerly Twitter)
Share May 30, 2025 on Linkedin
Email May 30, 2025 link
- Work on the west side of the intersection began May 12th.
- Placed pole bases.
- Excavation ongoing.
- Curb and gutter ongoing.
- Work on the west side of the intersection began May 12th.
- Placed pole bases.
- Excavation ongoing.
- Curb and gutter ongoing.
This project is substantially complete.
-
Share May 16, 2025 on Facebook
Share May 16, 2025 on X (formerly Twitter)
Share May 16, 2025 on Linkedin
Email May 16, 2025 link
- Removed asphalt.
- Installing storm drain.
- Prepping for curb and sidewalk.
- Removed asphalt.
- Installing storm drain.
- Prepping for curb and sidewalk.
This project is substantially complete.
-
Share May 8, 2025 on Facebook
Share May 8, 2025 on X (formerly Twitter)
Share May 8, 2025 on Linkedin
Email May 8, 2025 link
- Contractor working on the east side of the intersection.
- Signage and pavement marking remain on east side.
- Work on the west side of the intersection begins May 12th.
- Removals starting.
- Contractor working on the east side of the intersection.
- Signage and pavement marking remain on east side.
- Work on the west side of the intersection begins May 12th.
- Removals starting.
This project is substantially complete.
-
Share May 2, 2025 on Facebook
Share May 2, 2025 on X (formerly Twitter)
Share May 2, 2025 on Linkedin
Email May 2, 2025 link
- Contractor working on the east side of the intersection
- Sidewalk, curb and gutter complete
- Raised intersection placed
- Paving anticipated week of May 5th
- Contractor working on the east side of the intersection
- Sidewalk, curb and gutter complete
- Raised intersection placed
- Paving anticipated week of May 5th
This project is substantially complete.
-
Share April 25, 2025 on Facebook
Share April 25, 2025 on X (formerly Twitter)
Share April 25, 2025 on Linkedin
Email April 25, 2025 link
- Contractor working on the east side of the intersection.
- Sidewalk, curb and gutter complete.
- Forming for raised intersection.
- Placing concrete next week.
- Contractor working on the east side of the intersection.
- Sidewalk, curb and gutter complete.
- Forming for raised intersection.
- Placing concrete next week.
This project is substantially complete.
-
Share April 17, 2025 on Facebook
Share April 17, 2025 on X (formerly Twitter)
Share April 17, 2025 on Linkedin
Email April 17, 2025 link
- Contractor working on the east side of the intersection.
- Sidewalk, curb and gutter complete.
- Forming for raised intersection.
- Contractor working on the east side of the intersection.
- Sidewalk, curb and gutter complete.
- Forming for raised intersection.
This project is substantially complete.
-
Share April 11, 2025 on Facebook
Share April 11, 2025 on X (formerly Twitter)
Share April 11, 2025 on Linkedin
Email April 11, 2025 link
- Contractor working on the east side of the intersection.
- Ped ramps and existing signal poles removed.
- RRFB poles placed, waiting on cure.
- Prepping for curb and sidewalk.
- Curb and gutter placed.
- Ped ramps placed.
- Forming for raised intersection.
- Contractor working on the east side of the intersection.
- Ped ramps and existing signal poles removed.
- RRFB poles placed, waiting on cure.
- Prepping for curb and sidewalk.
- Curb and gutter placed.
- Ped ramps placed.
- Forming for raised intersection.
This project is substantially complete.