April 11, 2025

11 Apr 2025
  • Contractor working on the east side of the intersection.
  • Ped ramps and existing signal poles removed.
  • RRFB poles placed, waiting on cure.
  • Prepping for curb and sidewalk.
  • Curb and gutter placed.
  • Ped ramps placed.
  • Forming for raised intersection.