April 4, 2025

  • Contractor working on the east side of the intersection.
  • Ped ramps and existing signal poles removed.
  • RRFB poles placed, waiting on cure.
  • Prepping for curb and sidewalk.
  • Curb and gutter placed.
  • Ped ramps ongoing.
  • Storm drain manhole complete.
Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link

This project is substantially complete. 