March 28, 2025

  • Contractor working on the east side of the intersection.
  • Ped ramps and existing signal poles removed.
  • RRFB poles placed, waiting on cure.
  • Prepping for curb and sidewalk.
Share March 28, 2025 on Facebook Share March 28, 2025 on X (formerly Twitter) Share March 28, 2025 on Linkedin Email March 28, 2025 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>