March 6, 2025
- Work started March 3rd.
- Contractor working on the east side of the intersection.
- Ped ramps removed.
- Existing signal poles removed.
- Electric underground starting March 10th.
Share March 6, 2025 on Facebook
Share March 6, 2025 on Twitter
Share March 6, 2025 on Linkedin
Email March 6, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends