April 12, 2024

9th and Bannock

  • Waterline work by Veolia is complete.
  • ACHD’s project started March 4th .
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • New signal installation is on-going.
  • Concrete sidewalk work and brick work is complete.
  • Removal of existing asphalt is complete.
  • Concrete paving started April 12th and will be on-going for the next two weeks.
  • Work is weather dependent.
Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link

This project is substantially complete. 