April 12, 2024

9th and Bannock

  • Waterline work by Veolia is complete.
  • ACHD’s project started March 4th .
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • New signal installation is on-going.
  • Concrete sidewalk work and brick work is complete.
  • Removal of existing asphalt is complete.
  • Concrete paving started April 12th and will be on-going for the next two weeks.
  • Work is weather dependent.
Share April 12, 2024 on Facebook Share April 12, 2024 on X (formerly Twitter) Share April 12, 2024 on Linkedin Email April 12, 2024 link

This project is substantially complete. 