April 12, 2024
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work and brick work is complete.
- Removal of existing asphalt is complete.
- Concrete paving started April 12th and will be on-going for the next two weeks.
- Work is weather dependent.