Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
This project is substantially complete.
-
Share June 7, 2024 on Facebook
Share June 7, 2024 on X (formerly Twitter)
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st and includes manhole adjustments, permanent pavement markings, and activation of the pedestrian signal at Shoup.
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st and includes manhole adjustments, permanent pavement markings, and activation of the pedestrian signal at Shoup.
This project is substantially complete.
-
Share May 31, 2024 on Facebook
Share May 31, 2024 on X (formerly Twitter)
Share May 31, 2024 on Linkedin
Email May 31, 2024 link
- Roadway work began May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
- Existing asphalt has been removed.
- Contractor is re-grading the base gravels.
- Asphalt paving is scheduled to start the week of June 3rd.
- Roadway work began May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
- Existing asphalt has been removed.
- Contractor is re-grading the base gravels.
- Asphalt paving is scheduled to start the week of June 3rd.
This project is substantially complete.
-
Share May 23, 2024 on Facebook
Share May 23, 2024 on X (formerly Twitter)
Share May 23, 2024 on Linkedin
Email May 23, 2024 link
Maple Grove - I84 Work
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
Maple Grove - I84 Work
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
This project is substantially complete.
-
Share May 16, 2024 - Detour Map & Update Maple Grove on Facebook
Share May 16, 2024 - Detour Map & Update Maple Grove on X (formerly Twitter)
Share May 16, 2024 - Detour Map & Update Maple Grove on Linkedin
Email May 16, 2024 - Detour Map & Update Maple Grove link
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.

- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.

This project is substantially complete.
-
Share May 10, 2024 on Facebook
Share May 10, 2024 on X (formerly Twitter)
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
- Maple Grove Road, I-84 Overpass to Franklin Road -
- Concrete work is complete.
- Roadway work is postponed to 2024.
- Work anticipated to begin as early as June 3rd.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed through the work zone.
- Maple Grove Road, I-84 Overpass to Franklin Road -
- Concrete work is complete.
- Roadway work is postponed to 2024.
- Work anticipated to begin as early as June 3rd.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed through the work zone.
This project is substantially complete.
-
Share May 3, 2024 on Facebook
Share May 3, 2024 on X (formerly Twitter)
Share May 3, 2024 on Linkedin
Email May 3, 2024 link
9th and Bannock has been completed.
9th and Bannock has been completed.
This project is substantially complete.
-
Share April 25, 2024 on Facebook
Share April 25, 2024 on X (formerly Twitter)
Share April 25, 2024 on Linkedin
Email April 25, 2024 link
- 9th Street, Idaho Street to Bannock Street
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving was completed April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation. Some work is weather dependent.
- Anticipate opening the road at least partially on May 3rd.
- 9th Street, Idaho Street to Bannock Street
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving was completed April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation. Some work is weather dependent.
- Anticipate opening the road at least partially on May 3rd.
This project is substantially complete.
-
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving is anticipated to be complete April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation.
- Some work is weather dependent
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving is anticipated to be complete April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation.
- Some work is weather dependent
This project is substantially complete.
-
Share April 12, 2024 on Facebook
Share April 12, 2024 on X (formerly Twitter)
Share April 12, 2024 on Linkedin
Email April 12, 2024 link
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work and brick work is complete.
- Removal of existing asphalt is complete.
- Concrete paving started April 12th and will be on-going for the next two weeks.
- Work is weather dependent.
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work and brick work is complete.
- Removal of existing asphalt is complete.
- Concrete paving started April 12th and will be on-going for the next two weeks.
- Work is weather dependent.
This project is substantially complete.