April 14, 2023
- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Waterline work by Veolia at Bluegrass and Peachtree began April 11th. The intersection will be closed during the work. Waterline work by Veolia at Bluegrass and Elmer is scheduled to begin April 17th. Bluegrass will be closed between Elmer and Castle Drive.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Waterline work by Veolia is scheduled to begin April 24th. Castle Hill Way will be closed during the work.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work started April 5th. Lane restrictions will be in place for the duration of the work.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is ongoing. Road is closed for pipework.
- Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
- Spaulding St., Phillippi St. to Orchard St. - Water line replacement by Veolia has started February 27th in advance of ACHD's project. Concrete work is complete. Pipe work is complete.
- Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps
Share April 14, 2023 on Facebook
Share April 14, 2023 on Twitter
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
This project is substantially complete.