April 19, 2024
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving is anticipated to be complete April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation.
- Some work is weather dependent
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
This project is substantially complete.