April 28, 2023
- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Contractor is working on storm drain improvements. Bluegrass Ave and Elmer St will be closed May 1st - May 3rd. Bluegrass Ave & Castle Dr. will be closed May 4th - May 5th.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Waterline work by Veolia April 24th and is ongoing. Castle Hill way will be closed during Veolia's work.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work started April 5th. Lane restrictions will be in place for the duration of the work. Roadway work is scheduled to begin June 8th. Maple Grove Road will be closed during the work, which is anticipated to last a month.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is ongoing. Pipework is complete. Spaulding Street, Philippi Street to Orchard Street - Pipework and concrete work is complete. Roadway work is anticipated to start May 8th. Spaulding Street will be closed during the work, which is anticipated to last a month.
- Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
- Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
- Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia is anticipated to start May 1st. Turret Way will be closed during Veolia's work.