April 5, 2024
- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is complete.
- Brick replacement is on-going.
- Removal of existing asphalt is complete.
- Concrete paving is scheduled.
Share April 5, 2024 on Facebook
Share April 5, 2024 on X (formerly Twitter)
Share April 5, 2024 on Linkedin
Email April 5, 2024 link
This project is substantially complete.