April 5, 2024

  • 9th Street, Idaho Street to Bannock Street
    • Waterline work by Veolia is complete.
    • ACHD’s project started March 4th.
    • 9th Street will be closed during the work.
    • The existing signal at 9th Street & Bannock Street has been removed.
    • New signal installation is on-going.
    • Concrete sidewalk work is complete.
    • Brick replacement is on-going.
    • Removal of existing asphalt is complete.
    • Concrete paving is scheduled.
Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link

This project is substantially complete. 