June 9, 2023
- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work started May 29th and is ongoing.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is expected to be completed June 9th.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete work is complete.
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work began May 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
- Roosevelt St., Emerald St. to Irving St. - Concrete work is complete. Milling and paving is scheduled for the week of June 12th.
- Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Asphalt paving is complete. Minor work remains including speed hump installation, manhole adjustments, and permanent striping.
- Turret Way, Drawbridge Dr. to Castle Dr. - Pipe and storm drain work is scheduled to begin June 12th. Turret Way will be closed between Kennecott Street and Hallmark Street during the work.