August 25, 2023

9th Street, Idaho Street to Bannock Street

  • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

20th Street, Lemp Street to Irene Street

  • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
  • The segment between Ridenbaugh to Hazel is currently closed.

Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

  • Complete.

Castle Hill Way, Castle Drive to Drawbridge Drive

  • Pipe work is complete.
  • Concrete is complete.
  • Milling and paving is complete.
  • Minor work remains.

Turret Way, Drawbridge Drive to Castle Drive

  • Pipe and storm drain work is complete.
  • Concrete work is nearly complete.
  • Removal of asphalt is scheduled for August 25th.
  • The road will be closed for reconstruction beginning August 28th.

Morris Hill Road, west of Liberty Street to Hartman Street

  • Complete.

Spaulding Street, Philippi Street to Orchard Street

  • Complete.

Roosevelt Street, Emerald Street to Irving Street

  • Complete

Maple Grove Road, I-84 Overpass to Franklin Road

  • Concrete work is complete.
  • Roadway work is delayed until Spring 2024.

Amity Road, Enterprise Street to Production Avenue

  • Asphalt paving is complete. Minor work remains.

Enterprise Street, Amity Road to Commerce Avenue

  • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
Share August 25, 2023 on Facebook Share August 25, 2023 on Twitter Share August 25, 2023 on Linkedin Email August 25, 2023 link

This project is substantially complete. 