August 31, 2023

9th Street, Idaho Street to Bannock Street

  • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

20th Street, Lemp Street to Irene Street

  • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
  • The segment between Ridenbaugh to Hazel is currently closed.

Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

  • Complete.

Castle Hill Way, Castle Drive to Drawbridge Drive

  • Pipe work is complete.
  • Concrete is complete.
  • Milling and paving is complete.
  • Minor work remains.

Turret Way, Drawbridge Drive to Castle Drive

  • Pipe and storm drain work is complete.
  • Concrete work is nearly complete.
  • Removal of asphalt is scheduled for August 25th.
  • The road will be closed for reconstruction beginning August 28th.

Morris Hill Road, west of Liberty Street to Hartman Street

  • Complete.

Spaulding Street, Philippi Street to Orchard Street

  • Complete.

Roosevelt Street, Emerald Street to Irving Street

  • Complete

Maple Grove Road, I-84 Overpass to Franklin Road

  • Concrete work is complete.
  • Roadway work is delayed until Spring 2024.

Amity Road, Enterprise Street to Production Avenue

  • Asphalt paving is complete. Minor work remains.

Enterprise Street, Amity Road to Commerce Avenue

  • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
Share August 31, 2023 on Facebook Share August 31, 2023 on X (formerly Twitter) Share August 31, 2023 on Linkedin Email August 31, 2023 link

This project is substantially complete. 