August 31, 2023
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
- The segment between Ridenbaugh to Hazel is currently closed.
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Complete.
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete.
- Concrete is complete.
- Milling and paving is complete.
- Minor work remains.
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work is complete.
- Concrete work is nearly complete.
- Removal of asphalt is scheduled for August 25th.
- The road will be closed for reconstruction beginning August 28th.
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
Spaulding Street, Philippi Street to Orchard Street
- Complete.
Roosevelt Street, Emerald Street to Irving Street
- Complete
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is delayed until Spring 2024.
Amity Road, Enterprise Street to Production Avenue
- Asphalt paving is complete. Minor work remains.
Enterprise Street, Amity Road to Commerce Avenue
- Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.