August 4, 2023
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is anticipated to start in September. 9th Street will be closed during the work.
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
- The segment between Ridenbaugh to Hazel is currently closed.
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Complete.
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete.
- Concrete work on-going.
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work is complete.
- Concrete work is on-going.
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
Spaulding Street, Philippi Street to Orchard Street
- Complete.
Roosevelt Street, Emerald Street to Irving Street
- Complete
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
Amity Road, Enterprise Street to Production Avenue
- Asphalt paving is complete. Minor work remains.
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete. Roadway work started July 31st.. Enterprise Street will be closed between Amity and Boeing during the work, which is expected to last a month. Enterprise Street between Boeing and Commerce will be done over two weekends beginning August 18th.
Share August 4, 2023 on Facebook
Share August 4, 2023 on X (formerly Twitter)
Share August 4, 2023 on Linkedin
Email August 4, 2023 link
This project is substantially complete.