July 28, 2023
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is anticipated to start in mid-August. 9th Street will be closed during the work.
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to is complete.
- The segment between Ridenbaugh to Hazel is currently closed.
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Complete.
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete.
- Concrete work on-going.
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work is complete.
- Concrete work is on-going.
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
Spaulding Street, Philippi Street to Orchard Street
- Complete.
Roosevelt Street, Emerald Street to Irving Street
- Complete
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
Amity Road, Enterprise Street to Production Avenue
- Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month. Asphalt paving is scheduled to be complete on July 28th.
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete. Roadway work will begin after Amity is complete, anticipated for July 31st. Enterprise Street will be closed between Amity and Boeing during the work, which is expected to last a month.
Share July 28, 2023 on Facebook
Share July 28, 2023 on Twitter
Share July 28, 2023 on Linkedin
Email July 28, 2023 link
This project is substantially complete.