July 7, 2023

  • 20th Street, Lemp Street to Irene Street
    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be closed first, after which the segment between Ridenbaugh to Hazel will be closed.
  • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
    • Pipe work is complete.
    • Concrete work is nearly complete.
    • Milling and paving is scheduled for the week of July 10th.
  • Castle Hill Way, Castle Drive to Drawbridge Drive
    • Pipe work is complete. Concrete work started July 3rd and in on-going.
  • Turret Way, Drawbridge Drive to Castle Drive
    • Pipe and storm drain work is complete.
  • Morris Hill Road, west of Liberty Street to Hartman Street
    • Complete.
  • Spaulding Street, Philippi Street to Orchard Street
    • Complete.
  • Roosevelt Street, Emerald Street to Irving Street
    • Complete.
  • Maple Grove Road, I-84 Overpass to Franklin Road
    • Concrete work is complete.
  • Amity Road, Enterprise Street to Production Avenue
    • Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month.
  • Enterprise Street, Amity Road to Commerce Avenue
    • Concrete and pipe work are complete.
Share July 7, 2023 on Facebook Share July 7, 2023 on Twitter Share July 7, 2023 on Linkedin Email July 7, 2023 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>