June 14, 2024
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
Share June 14, 2024 on Facebook
Share June 14, 2024 on X (formerly Twitter)
Share June 14, 2024 on Linkedin
Email June 14, 2024 link
This project is substantially complete.