June 14, 2024
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
Share June 14, 2024 on Facebook
Share June 14, 2024 on Twitter
Share June 14, 2024 on Linkedin
Email June 14, 2024 link
This project is substantially complete.