June 2, 2023

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
  • 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work started May 29th and is ongoing.
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is scheduled to begin June 5th. Castle Hill Way will be closed during the work.
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete work is complete.
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work began may 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
  • Roosevelt St., Emerald St. to Irving St. - Concrete work is complete.
  • Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Spaulding Street will be closed during the work, which is anticipated to last a month. Asphalt paving is scheduled to be complete the week of June 5th.
  • Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia started May 4th. Turret Way will be closed during Veolia's work through June 4th.
Share June 2, 2023 on Facebook Share June 2, 2023 on Twitter Share June 2, 2023 on Linkedin Email June 2, 2023 link

This project is substantially complete. 