June 2, 2023

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
  • 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work started May 29th and is ongoing.
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is scheduled to begin June 5th. Castle Hill Way will be closed during the work.
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete work is complete.
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work began may 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
  • Roosevelt St., Emerald St. to Irving St. - Concrete work is complete.
  • Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Spaulding Street will be closed during the work, which is anticipated to last a month. Asphalt paving is scheduled to be complete the week of June 5th.
  • Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia started May 4th. Turret Way will be closed during Veolia's work through June 4th.
Share June 2, 2023 on Facebook Share June 2, 2023 on X (formerly Twitter) Share June 2, 2023 on Linkedin Email June 2, 2023 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>