March 15, 2024

  • 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete. ACHD’s project started March 4th.
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • New signal installation is on-going.
  • Concrete demolition is nearly complete.
  • Concrete sidewalk work is on-going.
  • Alley work on the west side of 9th Street started March 14th.
  • The alley is expected to reopen the afternoon of March 18th.
Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link

This project is substantially complete. 