March 29, 2024
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is scheduled to be done the week of March 25th.
- Removal of existing asphalt is scheduled to start March 28th.
- Concrete paving is scheduled to start the week of April 1st.