March 29, 2024

  • Waterline work by Veolia is complete.
  • ACHD’s project started March 4th.
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • New signal installation is on-going.
  • Concrete sidewalk work is scheduled to be done the week of March 25th.
  • Removal of existing asphalt is scheduled to start March 28th.
  • Concrete paving is scheduled to start the week of April 1st.
Share March 29, 2024 on Facebook Share March 29, 2024 on X (formerly Twitter) Share March 29, 2024 on Linkedin Email March 29, 2024 link

This project is substantially complete. 