March 29, 2024

  • Waterline work by Veolia is complete.
  • ACHD’s project started March 4th.
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • New signal installation is on-going.
  • Concrete sidewalk work is scheduled to be done the week of March 25th.
  • Removal of existing asphalt is scheduled to start March 28th.
  • Concrete paving is scheduled to start the week of April 1st.
Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>