March 3, 2023
- 9th St., Idaho St. to Bannock St.
- 20th St., Lemp St. to Irene St.
- Amity Rd., Enterprise St. to Production St.
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr.
- Castle Hill Way, Castle Dr. to Drawbridge Dr.
- Drawbridge Dr., West End to Castle Hill Way
- Enterprise St., Amity Rd. to Commerce Ave.
- Maple Grove Rd., I-84 Bridge to Franklin Rd.
- Morris Hill Rd., west of Liberty St. to Hartman St.
- Roosevelt St., Emerald St. to Irving St.
-
Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
- Water line replacement by Veolia started February 27th in advance of ACHD's project.
- Turret Way, Drawbridge Dr. to Castle Dr.
Share March 3, 2023 on Facebook
Share March 3, 2023 on Twitter
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
This project is substantially complete.