March 8, 2024

9th and Bannock

  • Waterline work by Veolia is complete.
  • ACHD’s project started March 4th .
  • 9th Street will be closed during the work.
  • The existing signal at 9th Street & Bannock Street has been removed.
  • Concrete demolition on-going.
  • Concrete pour today for signal bases.
  • Concrete sidewalk work starts next week.
Share March 8, 2024 on Facebook Share March 8, 2024 on X (formerly Twitter) Share March 8, 2024 on Linkedin Email March 8, 2024 link

This project is substantially complete. 