May 10, 2024

  • Maple Grove Road, I-84 Overpass to Franklin Road -
  • Concrete work is complete.
  • Roadway work is postponed to 2024.
  • Work anticipated to begin as early as June 3rd.
  • Maple Grove Road will be closed for approximately 4 weeks.
  • Local traffic will be allowed through the work zone.
Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link

This project is substantially complete. 