May 12, 2023

  • 9th Street, Idaho Street to Bannock Street
  • 20th Street, Lemp Street to Irene Street
  • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
    • Pipe work is complete.
  • Castle Hill Way, Castle Drive to Drawbridge Drive
  • Drawbridge Drive, west of Crimson Drive to Turret Way
  • Turret Way, Drawbridge Drive to Castle Drive
    • Waterline work by Veolia started May 4th.
    • Turret Way will be closed during Veolia’s work.
  • Morris Hill Road, west of Liberty Street to Hartman Street
    • Concrete work is ongoing.
    • Pipe work is complete.
  • Spaulding Street, Philippi Street to Orchard Street
    • Pipe work is complete.
    • Concrete work is complete.
    • Roadway work started May 8th. Spaulding Street will be closed during the work, which is anticipated to last a month.
  • Roosevelt Street, Emerald Street to Irving Street
    • Concrete work started May 9th.
  • Maple Grove Road, I-84 Overpass to Franklin Road
    • Concrete work is complete.
    • Roadway work is scheduled to begin June 8th. Maple Grove Road will be closed during the work, which is anticipated to last a month.
  • Amity Road, Enterprise Street to Production Avenue
  • Enterprise Street, Amity Road to Commerce Avenue
Share May 12, 2023 on Facebook Share May 12, 2023 on X (formerly Twitter) Share May 12, 2023 on Linkedin Email May 12, 2023 link

This project is substantially complete. 