May 31, 2024

  • Roadway work began May 28th.
  • Maple Grove Road will be closed for approximately 4 weeks.
  • Local traffic will be allowed at Franklin Road.
  • Existing asphalt has been removed.
  • Contractor is re-grading the base gravels.
  • Asphalt paving is scheduled to start the week of June 3rd.
Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>