May 31, 2024

  • Roadway work began May 28th.
  • Maple Grove Road will be closed for approximately 4 weeks.
  • Local traffic will be allowed at Franklin Road.
  • Existing asphalt has been removed.
  • Contractor is re-grading the base gravels.
  • Asphalt paving is scheduled to start the week of June 3rd.
Share May 31, 2024 on Facebook Share May 31, 2024 on X (formerly Twitter) Share May 31, 2024 on Linkedin Email May 31, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>