May 31, 2024
- Roadway work began May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
- Existing asphalt has been removed.
- Contractor is re-grading the base gravels.
- Asphalt paving is scheduled to start the week of June 3rd.
Share May 31, 2024 on Facebook
Share May 31, 2024 on X (formerly Twitter)
Share May 31, 2024 on Linkedin
Email May 31, 2024 link
This project is substantially complete.