October 12, 2023
- 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
- 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Roadway work between Hazel and Irene will begin October 16th. Roadway work between Lemp and Hazel will follow.
- Amity Rd., Enterprise St. to Production St. - Complete.
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
- Drawbridge Dr., West End to Castle Hill Way - Concrete work is complete. Milling and paving is scheduled for October 9 -10.
- Enterprise St., Amity Rd. to Commerce Ave. - Asphalt paving is complete. Minor work remains.
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
- Roosevelt St., Emerald St. to Irving St. - Complete.
- Spaulding St., Phillippi St. to Orchard St. - Complete.
- Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
Share October 12, 2023 on Facebook
Share October 12, 2023 on Twitter
Share October 12, 2023 on Linkedin
Email October 12, 2023 link
This project is substantially complete.