October 20, 2023

  • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
  • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Roadway work between Hazel and Irene will begin October 16th and is expected to take two weeks. Roadway work between Lemp and Hazel will follow.
  • Amity Rd., Enterprise St. to Production St. - Complete.
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
  • Drawbridge Dr., West End to Castle Hill Way - Complete.
  • Enterprise St., Amity Rd. to Commerce Ave. - Complete.
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
  • Roosevelt St., Emerald St. to Irving St. - Complete.
  • Spaulding St., Phillippi St. to Orchard St. - Complete.
  • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
Share October 20, 2023 on Facebook Share October 20, 2023 on Twitter Share October 20, 2023 on Linkedin Email October 20, 2023 link

This project is substantially complete. 