October 6, 2023

  • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
  • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. ACHD's contractor started pipe work on September 5th. The road will remain closed. Concrete work is ongoing.
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
  • Drawbridge Dr., West End to Castle Hill Way - Concrete work is complete. Milling and paving is scheduled for October 9 -10.
  • Enterprise St., Amity Rd. to Commerce Ave. - Asphalt paving is complete. Minor work remains.
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
  • Roosevelt St., Emerald St. to Irving St. - Complete.
  • Spaulding St., Phillippi St. to Orchard St. - Complete.
  • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link

This project is substantially complete. 