September 15, 2023

9th Street, Idaho Street to Bannock Street

  • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

20th Street, Lemp Street to Irene Street

  • Waterline work by Veolia is complete. ▪ ACHD’s contractor started pipe work on September 5th.
  • The road will remain closed.

Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

  • Complete.

Castle Hill Way, Castle Drive to Drawbridge Drive

  • Paving is complete.
  • Minor work remains.

Turret Way, Drawbridge Drive to Castle Drive

  • Pipe and storm drain work is complete.
  • Concrete work is nearly complete.
  • The road will be closed for reconstruction beginning August 28th through mid-September. Asphalt paving is scheduled for the week of September 18th.

Drawbridge Drive, west of Crimson Drive to Turret Way

  • Concrete work is on-going.

Morris Hill Road, west of Liberty Street to Hartman Street

  • Complete.

Spaulding Street, Philippi Street to Orchard Street

  • Complete.

Roosevelt Street, Emerald Street to Irving Street

  • Complete

Maple Grove Road, I-84 Overpass to Franklin Road

  • Concrete work is complete.
  • Roadway work is delayed until Spring 2024.

Amity Road, Enterprise Street to Production Avenue

  • Asphalt paving is complete. Minor work remains.

Enterprise Street, Amity Road to Commerce Avenue

  • Asphalt paving is complete. Minor work remains.
Share September 15, 2023 on Facebook Share September 15, 2023 on X (formerly Twitter) Share September 15, 2023 on Linkedin Email September 15, 2023 link

This project is substantially complete. 