September 22, 2023
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia started September 5th. 9th Street will be closed during the work.
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia is complete. ACHD’s contractor started pipe work on September 5th.
- The road will remain closed.
- Concrete work ongoing.
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Complete.
Castle Hill Way, Castle Drive to Drawbridge Drive
- Complete.
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work is complete.
- Concrete work is complete.
- The road will be closed for reconstruction beginning August 28th through mid-September. Asphalt paving is scheduled for September 25-26th.
Drawbridge Drive, west of Crimson Drive to Turret Way
- Concrete work is complete.
- Milling and paving is scheduled for October 9-10th.
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
Spaulding Street, Philippi Street to Orchard Street
- Complete.
Roosevelt Street, Emerald Street to Irving Street
- Complete
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is delayed until Spring 2024.
Amity Road, Enterprise Street to Production Avenue
- Asphalt paving is complete. Minor work remains.
Enterprise Street, Amity Road to Commerce Avenue
- Asphalt paving is complete. Minor work remains.
Share September 22, 2023 on Facebook
Share September 22, 2023 on Twitter
Share September 22, 2023 on Linkedin
Email September 22, 2023 link
This project is substantially complete.