September 29, 2023
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia started September 5th. 9th Street will be closed during the work.
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia is complete. ACHD’s contractor started pipe work on September 5th.
- The road will remain closed.
- Concrete work ongoing.
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Complete.
Castle Hill Way, Castle Drive to Drawbridge Drive
- Complete.
Turret Way, Drawbridge Drive to Castle Drive
- Asphalt paving is complete. Minor work remains.
Drawbridge Drive, west of Crimson Drive to Turret Way
- Concrete work is complete.
- Milling and paving is scheduled for October 9-10th.
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
Spaulding Street, Philippi Street to Orchard Street
- Complete.
Roosevelt Street, Emerald Street to Irving Street
- Complete
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is delayed until Spring 2024.
Amity Road, Enterprise Street to Production Avenue
- Asphalt paving is complete. Minor work remains.
Enterprise Street, Amity Road to Commerce Avenue
- Asphalt paving is complete. Minor work remains.
Share September 29, 2023 on Facebook
Share September 29, 2023 on X (formerly Twitter)
Share September 29, 2023 on Linkedin
Email September 29, 2023 link
This project is substantially complete.