September 8, 2023

9th Street, Idaho Street to Bannock Street

  • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

20th Street, Lemp Street to Irene Street

  • Waterline work by Veolia is complete. ▪ ACHD’s contractor started pipe work on September 5th.
  • The road will remain closed.

Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

  • Complete.

Castle Hill Way, Castle Drive to Drawbridge Drive

  • Paving is complete.
  • Minor work remains.

Turret Way, Drawbridge Drive to Castle Drive

  • Pipe and storm drain work is complete.
  • Concrete work is nearly complete.
  • The road will be closed for reconstruction beginning August 28th through mid-September.

Drawbridge Drive, west of Crimson Drive to Turret Way

  • Concrete work is on-going.

Morris Hill Road, west of Liberty Street to Hartman Street

  • Complete.

Spaulding Street, Philippi Street to Orchard Street

  • Complete.

Roosevelt Street, Emerald Street to Irving Street

  • Complete

Maple Grove Road, I-84 Overpass to Franklin Road

  • Concrete work is complete.
  • Roadway work is delayed until Spring 2024.

Amity Road, Enterprise Street to Production Avenue

  • Asphalt paving is complete. Minor work remains.

Enterprise Street, Amity Road to Commerce Avenue

  • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link

This project is substantially complete. 