-
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Asphalt paving is scheduled for late September.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Asphalt paving is scheduled for late September.
-
Share September 3, 2026 on Facebook
Share September 3, 2026 on X (formerly Twitter)
Share September 3, 2026 on Linkedin
Email September 3, 2026 link
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
-
Share August 28, 2026 on Facebook
Share August 28, 2026 on X (formerly Twitter)
Share August 28, 2026 on Linkedin
Email August 28, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
-
Share August 20, 2026 on Facebook
Share August 20, 2026 on X (formerly Twitter)
Share August 20, 2026 on Linkedin
Email August 20, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
-
Share August 14, 2026 on Facebook
Share August 14, 2026 on X (formerly Twitter)
Share August 14, 2026 on Linkedin
Email August 14, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
-
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
- Project includes work on the following segments:
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th
- Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Project includes work on the following segments:
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th
- Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
-
Share July 30, 2026 on Facebook
Share July 30, 2026 on X (formerly Twitter)
Share July 30, 2026 on Linkedin
Email July 30, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
-
Share July 23, 2026 on Facebook
Share July 23, 2026 on X (formerly Twitter)
Share July 23, 2026 on Linkedin
Email July 23, 2026 link
Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements.
Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements.
-
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on drainage improvements.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on drainage improvements.
-
Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.