-
Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.
-
Share July 1, 2026 on Facebook
Share July 1, 2026 on X (formerly Twitter)
Share July 1, 2026 on Linkedin
Email July 1, 2026 link
- Work is anticipated to begin July 6th. Goldenrod will be closed during the work.
- Work is anticipated to begin July 6th. Goldenrod will be closed during the work.
-
Share June 26, 2026 - Goldenrod on Facebook
Share June 26, 2026 - Goldenrod on X (formerly Twitter)
Share June 26, 2026 - Goldenrod on Linkedin
Email June 26, 2026 - Goldenrod link
- Goldenrod Avenue, west end to Cloverdale Road.
- Work is anticipated to begin July 6th.
- Goldenrod will be closed during the work.
- Goldenrod Avenue, west end to Cloverdale Road.
- Work is anticipated to begin July 6th.
- Goldenrod will be closed during the work.
-
Share June 18, 2026 on Facebook
Share June 18, 2026 on X (formerly Twitter)
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
- PHB will be installed later this summer - waiting on electrical materials to be delivered.
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
- PHB will be installed later this summer - waiting on electrical materials to be delivered.
-
Share June 12, 2026 on Facebook
Share June 12, 2026 on X (formerly Twitter)
Share June 12, 2026 on Linkedin
Email June 12, 2026 link
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk work will continue the week of June 15th.
- Remaining asphalt patching is scheduled for June 25th.
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk work will continue the week of June 15th.
- Remaining asphalt patching is scheduled for June 25th.
-
Share June 5, 2026 on Facebook
Share June 5, 2026 on X (formerly Twitter)
Share June 5, 2026 on Linkedin
Email June 5, 2026 link
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
-
Share May 29, 2026 on Facebook
Share May 29, 2026 on X (formerly Twitter)
Share May 29, 2026 on Linkedin
Email May 29, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.
-
Share May 21, 2026 on Facebook
Share May 21, 2026 on X (formerly Twitter)
Share May 21, 2026 on Linkedin
Email May 21, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in early June.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in early June.
-
Share Goldenrod Avenue Improvements Begin This June on Facebook
Share Goldenrod Avenue Improvements Begin This June on X (formerly Twitter)
Share Goldenrod Avenue Improvements Begin This June on Linkedin
Email Goldenrod Avenue Improvements Begin This June link
Starting as early as June, the Ada County Highway District (ACHD) will start construction on Goldenrod Avenue between the west end and Cloverdale Road. Construction is expected to be complete by late 2026*
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- On-street parking restrictions
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
Starting as early as June, the Ada County Highway District (ACHD) will start construction on Goldenrod Avenue between the west end and Cloverdale Road. Construction is expected to be complete by late 2026*
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- On-street parking restrictions
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
-
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.