-
Share July 30, 2026 on Facebook
Share July 30, 2026 on X (formerly Twitter)
Share July 30, 2026 on Linkedin
Email July 30, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.
-
Share July 23, 2026 on Facebook
Share July 23, 2026 on X (formerly Twitter)
Share July 23, 2026 on Linkedin
Email July 23, 2026 link
Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements.
Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements.
-
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on drainage improvements.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on drainage improvements.
-
Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Contractor working on tree removal and asphalt removal, followed by drainage improvements.
-
Share July 1, 2026 on Facebook
Share July 1, 2026 on X (formerly Twitter)
Share July 1, 2026 on Linkedin
Email July 1, 2026 link
- Work is anticipated to begin July 6th. Goldenrod will be closed during the work.
- Work is anticipated to begin July 6th. Goldenrod will be closed during the work.
-
Share June 26, 2026 - Goldenrod on Facebook
Share June 26, 2026 - Goldenrod on X (formerly Twitter)
Share June 26, 2026 - Goldenrod on Linkedin
Email June 26, 2026 - Goldenrod link
- Goldenrod Avenue, west end to Cloverdale Road.
- Work is anticipated to begin July 6th.
- Goldenrod will be closed during the work.
- Goldenrod Avenue, west end to Cloverdale Road.
- Work is anticipated to begin July 6th.
- Goldenrod will be closed during the work.
-
Share June 18, 2026 on Facebook
Share June 18, 2026 on X (formerly Twitter)
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
- PHB will be installed later this summer - waiting on electrical materials to be delivered.
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
- PHB will be installed later this summer - waiting on electrical materials to be delivered.
-
Share June 12, 2026 on Facebook
Share June 12, 2026 on X (formerly Twitter)
Share June 12, 2026 on Linkedin
Email June 12, 2026 link
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk work will continue the week of June 15th.
- Remaining asphalt patching is scheduled for June 25th.
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk work will continue the week of June 15th.
- Remaining asphalt patching is scheduled for June 25th.
-
Share June 5, 2026 on Facebook
Share June 5, 2026 on X (formerly Twitter)
Share June 5, 2026 on Linkedin
Email June 5, 2026 link
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
-
Share May 29, 2026 on Facebook
Share May 29, 2026 on X (formerly Twitter)
Share May 29, 2026 on Linkedin
Email May 29, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.