-
Share October 30, 2026 - Goldenrod - Substantially Complete on Facebook
Share October 30, 2026 - Goldenrod - Substantially Complete on X (formerly Twitter)
Share October 30, 2026 - Goldenrod - Substantially Complete on Linkedin
Email October 30, 2026 - Goldenrod - Substantially Complete link
-
Share October 22, 2026 on Facebook
Share October 22, 2026 on X (formerly Twitter)
Share October 22, 2026 on Linkedin
Email October 22, 2026 link
- Mainline asphalt paving was completed October 20th.
- Minor work remains, including speed humps, miscellaneous paving, manhole adjustments, landscape repair, and fencing.
- Mainline asphalt paving was completed October 20th.
- Minor work remains, including speed humps, miscellaneous paving, manhole adjustments, landscape repair, and fencing.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share October 16, 2026 on Facebook
Share October 16, 2026 on X (formerly Twitter)
Share October 16, 2026 on Linkedin
Email October 16, 2026 link
Goldenrod Avenue, west end to Cloverdale Road
- Asphalt paving to start October 16th or the 19th.
- Minor work remains, including manhole adjustments, landscape repair, and fencing.
Goldenrod Avenue, west end to Cloverdale Road
- Asphalt paving to start October 16th or the 19th.
- Minor work remains, including manhole adjustments, landscape repair, and fencing.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share October 9, 2026 on Facebook
Share October 9, 2026 on X (formerly Twitter)
Share October 9, 2026 on Linkedin
Email October 9, 2026 link
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Contractor working on placement of base gravels.
- Asphalt paving is scheduled for October 14th – 16th , weather dependent.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Contractor working on placement of base gravels.
- Asphalt paving is scheduled for October 14th – 16th , weather dependent.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share October 2, 2026 on Facebook
Share October 2, 2026 on X (formerly Twitter)
Share October 2, 2026 on Linkedin
Email October 2, 2026 link
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Contractor working on placement of base gravels.
- Asphalt paving is scheduled for October 12th & 13th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Contractor working on placement of base gravels.
- Asphalt paving is scheduled for October 12th & 13th.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share September 17, 2026 - Goldenrod on Facebook
Share September 17, 2026 - Goldenrod on X (formerly Twitter)
Share September 17, 2026 - Goldenrod on Linkedin
Email September 17, 2026 - Goldenrod link
Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Asphalt paving is scheduled for October 1st, 2nd, and 3rd.
Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Asphalt paving is scheduled for October 1st, 2nd, and 3rd.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Asphalt paving is scheduled for late September.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Asphalt paving is scheduled for late September.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share September 3, 2026 on Facebook
Share September 3, 2026 on X (formerly Twitter)
Share September 3, 2026 on Linkedin
Email September 3, 2026 link
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share August 28, 2026 on Facebook
Share August 28, 2026 on X (formerly Twitter)
Share August 28, 2026 on Linkedin
Email August 28, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
- Edgewood Lane, Hill Road to Floating Feather Road
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share August 20, 2026 on Facebook
Share August 20, 2026 on X (formerly Twitter)
Share August 20, 2026 on Linkedin
Email August 20, 2026 link
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.