Allumbaugh Street | Edgewood Lane | Goldenrod Avenue

Share Allumbaugh Street | Edgewood Lane | Goldenrod Avenue on Facebook Share Allumbaugh Street | Edgewood Lane | Goldenrod Avenue on Twitter Share Allumbaugh Street | Edgewood Lane | Goldenrod Avenue on Linkedin Email Allumbaugh Street | Edgewood Lane | Goldenrod Avenue link

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments

  • Allumbaugh Street, Douglas Street to Fairmont Street- Reconstruct roadway; replace existing pedestrian ramps and driveway approaches to meet modern standards; install new sidewalk in existing gaps; reset existing Rapid Rectangular Flashing Beacon (RRFB)
  • Edgewood Lane, Harvey Street to Floating Feather Road- Remove and replace pavement; replace existing pedestrian ramps and driveway approaches to meet current accessibility standards; install new Pedestrian Hybrid Beacon (PHB) at Floating Feather Road; rebuild existing speed humps
  • Goldenrod Avenue, West End to Cloverdale Road- Remove and replace pavement; replace existing pedestrian ramps and driveway approaches to meet modern standards; install new sidewalk in existing gaps; install new Pedestrian Hybrid Beacon (PHB) at Cloverdale Road pedestrian crossing

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments

  • Allumbaugh Street, Douglas Street to Fairmont Street- Reconstruct roadway; replace existing pedestrian ramps and driveway approaches to meet modern standards; install new sidewalk in existing gaps; reset existing Rapid Rectangular Flashing Beacon (RRFB)
  • Edgewood Lane, Harvey Street to Floating Feather Road- Remove and replace pavement; replace existing pedestrian ramps and driveway approaches to meet current accessibility standards; install new Pedestrian Hybrid Beacon (PHB) at Floating Feather Road; rebuild existing speed humps
  • Goldenrod Avenue, West End to Cloverdale Road- Remove and replace pavement; replace existing pedestrian ramps and driveway approaches to meet modern standards; install new sidewalk in existing gaps; install new Pedestrian Hybrid Beacon (PHB) at Cloverdale Road pedestrian crossing
  • Edgewood Lane construction to start March 2nd

    Share Edgewood Lane construction to start March 2nd on Facebook Share Edgewood Lane construction to start March 2nd on Twitter Share Edgewood Lane construction to start March 2nd on Linkedin Email Edgewood Lane construction to start March 2nd link

    Starting March 2nd, the Ada County Highway District (ACHD) will start construction on Edgewood Lane between Harvey Street and Floating Feather Road. Construction is expected to be complete by early summer 2026*

    Construction Impacts

    • Temporary road closures
    • Pedestrian detours and sidewalk closures
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize impacts


    *Construction schedules may change.

    Edgewood Lane will be closed to through traffic from March 2 through early summer 2026, with access limited to local traffic and golf course visitors only



  • Pipe work to start late January

    Share Pipe work to start late January on Facebook Share Pipe work to start late January on Twitter Share Pipe work to start late January on Linkedin Email Pipe work to start late January link

    ACHD will begin pipe work on the following segments in late January 2025:

    • Allumbaugh Street, Douglas Street to Fairmont Street
    • Goldenrod Avenue, West End to Cloverdale Road

    The pipe work is expected to be completed by late March 2025, with crews starting on other parts of the project as early as April 2025.

    Expected Construction Impacts:

    • Temporary road and lane closures
    • Pedestrian detours and sidewalk closures
    • Lane restrictions
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Temporary on-street parking impacts
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize impacts and maintain access

    Emergency access will be accommodated if the need arises.

  • Winter 2025 Update

    Share Winter 2025 Update on Facebook Share Winter 2025 Update on Twitter Share Winter 2025 Update on Linkedin Email Winter 2025 Update link

    The following segments have been removed from this project due to limitations in funding:

    • Cole Road, Ustick Road to Kettering Avenue
    • Orchard Street, Emerald Street to Fairview Avenue
Page last updated: 20 Feb 2026, 02:46 PM