August 28, 2026
- Edgewood Lane, Hill Road to Floating Feather Road
- Substantially complete
- Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are on-going.
- Allumbaugh Street, Douglas Street to Fairmont Street
- Work will begin after the project on Liberty Street, Douglas to Denton is complete.