July 30, 2026
- Edgewood Lane, Hill Road to Floating Feather Road - Substantially complete.
- Goldenrod Avenue, west end to Cloverdale Road - Goldenrod will be closed during the project. Work began July 6th. Contractor working on drainage improvements and starting to prep for concrete improvements.
- Allumbaugh Street, Douglas Street to Fairmont Street - Work will begin after the project on Liberty Street, Douglas to Denton is complete.