June 18, 2026

Edgewood Lane, Hill Road to Floating Feather Road

  • Edgewood Lane was re-opened on June 5th.
  • Milling and mainline paving is complete.
  • Concrete sidewalk is nearly complete.
  • Minor asphalt patching remains.