June 18, 2026
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
Share June 18, 2026 on Facebook
Share June 18, 2026 on Twitter
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends