June 18, 2026
Edgewood Lane, Hill Road to Floating Feather Road
- Edgewood Lane was re-opened on June 5th.
- Milling and mainline paving is complete.
- Concrete sidewalk is nearly complete.
- Minor asphalt patching remains.
- PHB will be installed later this summer - waiting on electrical materials to be delivered.